Hangar Floor, Naval Air Station North Island (NASNI)

Delivery Type: Design-Bid-Build
Contract Value: $992,924
Size: 20,000 sq. ft.
Description: The purpose of this project was to resurface the hangar bay floor at Building 524.  The hangar is used for aircraft maintenance and washing, as well as special occasions. Key features:

  • Completed an industrial resurface of the hangar bay floor, meeting weight requirements to support a C-40 aircraft and support equipment.

  • Installed a moisture vapor barrier and a 5-layer epoxy mortar system with a 10-year warranty.

  • Provided floor striping and markings.

  • Required close coordination with Government representatives for access, storage, and accommodation of a Change of Command ceremony.